The North Pender Island Board of Variance approved application NP-BOV-2023.3, with a condition that the concrete footings and deck supports be sited at least 0.60 m farther back to the north from the deck’s encroachment within 5.64 m of the front lot line.[1]
The minutes say the applicant offered to reduce the deck from 8 feet to 7 feet or move its posts back by 2 feet.[1]
The board’s resolution said it found that complying with the setback provision would cause undue hardship to the applicant, and approved the application with the stated condition.[1]
The hearing was held electronically on June 13, 2023, and adjourned at 3:00 p.m.[1]
Sources
-
North Pender BOV Meeting Minutes — June 13, 2023
that having considered the matters set out in s.542(1)(c) of the Local Government Act, and having found that undue hardship would be caused to the applicant if s. 8.1.5 (a) of the North Pender Land use Bylaw No. 103, 1996 is complied with, the North Pender Island Board of Variance approves application NP-BOV-2023.3 (McDonald) as presented in Schedule ‘A’, of the NP-BOV-2023.3 Notice of Hearing, with the exception that the concrete footings and deck supports must be sited at least 0.60 m further back to the north away from the encroachment of the front edge of the deck located within 5.64 m of the front lot line.